If contractors and suppliers don’t get paid on a construction project in Rhode Island, they can file a mechanics lien to secure payment. A mechanics lien is a legal tool that provides the unpaid party with a security interest in the property. This page breaks down the rules, requirements, and deadlines you need to follow to file a Rhode Island mechanics lien.

Quicklinks

“Levelset takes something that is pretty complex and makes it easy.”

Ready to file a lien in Rhode Island?

Rhode Island lien law deadlines for:


Please Note: This section provides a quick-reference summary of deadlines and requirements only. For a comprehensive breakdown and complete details, refer to the FAQ section below.
Preliminary notice deadlines
10 days

Notice of Possible Mechanic's Lien required within 10 days of commencing work. Notice of Intent must be given to Owner within same 200-day period as lien.

Send Your Notice
Mechanics lien deadlines
200 days

Lien must be filed w/in 200 days after last labor or materials furnished.

Enforcement deadlines
40 days

In Rhode Island a Complaint to Enforce a Mechanics Lien must be filed within 40 days of the date on which the lien was filed.

A Notice of Lis Pendens must be filed before the Complaint to Enforce the lien is filed. However, the Complaint must be filed within 7 days after filing the Notice of Lis Pendens.

Preliminary notice deadlines
200 days

Notice of Intent must be given to Owner within same 200-day period as lien.

Send Your Notice
Mechanics lien deadlines
200 days

Lien must be filed w/in 200 days after last labor or materials furnished.

Enforcement deadlines
40 days

In Rhode Island a Complaint to Enforce a Mechanics Lien must be filed within 40 days of the date on which the lien was filed.

A Notice of Lis Pendens must be filed before the Complaint to Enforce the lien is filed. However, the Complaint must be filed within 7 days after filing the Notice of Lis Pendens.

Preliminary notice deadlines
200 days

Notice of Intent must be given to Owner within same 200-day period as lien.

Send Your Notice
Mechanics lien deadlines
200 days

Lien must be filed w/in 200 days after last labor or materials furnished.

Enforcement deadlines
40 days

In Rhode Island a Complaint to Enforce a Mechanics Lien must be filed within 40 days of the date on which the lien was filed.

A Notice of Lis Pendens must be filed before the Complaint to Enforce the lien is filed. However, the Complaint must be filed within 7 days after filing the Notice of Lis Pendens.